Surface Ops Track: Site Work, Heavy Equipment and Hauling · Module 4 of 5 · about 40 min

Keeping the site moving

The skill this builds. We compare a changing site plan with its critical path, record dependencies and give the next crew an accurate handoff.

A site runs on a plan everyone can see. The schedule is a chain of tasks that depend on each other, and the longest chain of dependent tasks is the critical path. If anything on it slips, the finish date slips. Tasks off the critical path have float: they can move a little without moving the end.

Crews work from a short lookahead, usually the next two or three weeks, pulled from the master schedule. Before a task starts, the foreman checks its constraints: materials on site, equipment running, permits signed, crew trained and the area ready. A task with an open constraint is a task that will stall with people standing around.

Mine sites have a formal version of the morning check. Under MSHA rule 30 CFR 56.18002, a competent person examines every working place at least once each shift before miners start work there, and records what was found before the shift ends. Construction sites run a toolbox talk or pre-task plan for the same reason.

The day ends with a daily report: hours, quantities, equipment, deliveries, weather, delays and incidents. That report settles disputes and change orders months later. Vague entries like "worked on drainage" are useless when someone asks why the job ran late.

Laydown matters more than people think. Material dropped in the wrong spot gets moved twice, blocks a haul road or gets damaged. Plan where each delivery lands, keep traffic one-way where you can, and keep people on foot apart from moving equipment.

We distinguish task duration, dependency and available float. A critical path is determined by the network of dependent tasks, not simply the task with the largest crew or the most visible machine. Off-path work can absorb some delay only while its available float remains. Changing a dependency or consuming that float can change the path, so a copied label from an old schedule is not evidence of the current controlling chain.

Worked example, fictional network: route A takes four days for preparation followed by three for installation, while independent route B takes five days. A final task waits for both. Route A therefore controls the start at seven days and B has two days of float relative to that join. A one-day delay on B does not move the join; a three-day delay makes B finish at eight and move it by one. We state that no other constraints or resource conflicts apply in this classroom example.

We also separate examining a working place from writing its record. The cited MSHA rule requires the competent-person examination before miners begin there, while the record is made before the shift ends. That later record deadline is not permission to postpone the examination. The record identifies the examiner, date, location and adverse conditions, with correction dates added as applicable. Different construction tasks need their own applicable requirements rather than an assumption that every mine rule covers every site.

Practice, on paper: we revise a fictional lookahead containing one material dependency, an access conflict and a delayed inspection record. We calculate a simple join, identify the actual constraint and write a factual daily entry with quantity, time and cause. Our self-check avoids reporting an unexamined area as ready or replacing a specific delay record with a vague statement that work continued.

Sources

Module quiz

10 questions, 8 correct to pass. You'll see what you missed and why, and you can retake it.

Practice exercise · about 30 min

Write the daily report

Daily reports are one of the first things a new lead hand is trusted with. Turn these scribbled notes into a report a project manager could rely on.

Situation

  • Notes: "crew 5 + me. ex 1, loader. rain started like 1:30?? quit trench at 2 maybe 2:15. 80ft pipe done, from MH-3 heading east. pump truck guy no show for tmrw call - need to confirm. Jose cut hand on bucket teeth, bandaid, back to work. inspector came 10am ok on bedding. fittings delivery short 2 tees."

Your task. Write the daily report in about 120 to 250 words. Fill gaps honestly: if something is unclear, say so instead of guessing. Add a short evidence check: distinguish observed facts from assumptions, connect two relevant controls from the lesson, and explain what the responsible reviewer must verify. This is a fictional desk exercise, not a live-work instruction.

0 words. Feedback is practice only and doesn't affect passing.