Join the crewDashboard

Surface Ops Track: Site Work, Heavy Equipment and Hauling · Module 4 of 5 · about 20 min

Keeping the site moving

The skill this builds. Hiring managers ask: "What do you do when the plan falls apart at 6 a.m.?" They want someone who protects the critical path, keeps people productive and writes it down accurately.

A site runs on a plan everyone can see. The schedule is a chain of tasks that depend on each other, and the longest chain of dependent tasks is the critical path. If anything on it slips, the finish date slips. Tasks off the critical path have float: they can move a little without moving the end.

Crews work from a short lookahead, usually the next two or three weeks, pulled from the master schedule. Before a task starts, the foreman checks its constraints: materials on site, equipment running, permits signed, crew trained and the area ready. A task with an open constraint is a task that will stall with people standing around.

Mine sites have a formal version of the morning check. Under MSHA rule 30 CFR 56.18002, a competent person examines every working place at least once each shift before miners start work there, and records what was found before the shift ends. Construction sites run a toolbox talk or pre-task plan for the same reason.

The day ends with a daily report: hours, quantities, equipment, deliveries, weather, delays and incidents. That report settles disputes and change orders months later. Vague entries like "worked on drainage" are useless when someone asks why the job ran late.

Laydown matters more than people think. Material dropped in the wrong spot gets moved twice, blocks a haul road or gets damaged. Plan where each delivery lands, keep traffic one-way where you can, and keep people on foot apart from moving equipment.

Sources

Module quiz

5 questions, 4 correct to pass. You'll see what you missed and why, and you can retake it.

Hands-on exercise · about 15 min

Write the daily report

Daily reports are one of the first things a new lead hand is trusted with. Turn these scribbled notes into a report a project manager could rely on.

Situation

  • Notes: "crew 5 + me. ex 1, loader. rain started like 1:30?? quit trench at 2 maybe 2:15. 80ft pipe done, from MH-3 heading east. pump truck guy no show for tmrw call - need to confirm. Jose cut hand on bucket teeth, bandaid, back to work. inspector came 10am ok on bedding. fittings delivery short 2 tees."

Your task. Write the daily report in about 120 to 250 words. Fill gaps honestly: if something is unclear, say so instead of guessing.

0 words. Feedback is practice only and doesn't affect passing.

Next: What your supervisor expects →